Last Updated: 05/04/2022

Project Update

May 04, 2022: An RFB has been released for the North Building Demo and Parking Lot Build Back.  Please see more information below under the Project Schedule.

Project Overview

Design and construction, including site development, for Village on Park Improvements located at 2300 South Park Street. The first phase of work includes demolition of the north wing of the Villager Mall building and construction of a new surface parking lot that is planned to be constructed and completed in the summer of 2022. The second phase of site development includes the new Urban League Hub building and the proposed parking structure garage. The parking structure will have approximately 295 parking stalls above grade with approximately 6-levels. It will operate as a fully automated self-parking structure. The Parking Structure project is part of the second phase of an overall master plan for the ongoing development of the Village on Park campus. The Urban League Black Business Hub building will be designed and constructed by the Urban League of Greater Madison and is planned to begin construction in the spring of 2022 with construction completion and occupancy in the summer of 2023. The new parking structure garage will provide tenant parking for the Urban League Hub tenants and other Village on Park/Villager Mall tenants and visitors.
 

For additional information please see the City of Madison DPCED Planning South Madison Plan

Project Schedule

City User Agency: Community Development Authority

Village on Park North Building Demo and Parking Lot Build Back

1st Advertisement of Bid: April 25, 2022 RFB documents can be found on Vendor Net and Demandstar
Pre-Bid Project Tour: May 5, 2022 @ 10:30 at the project site, 2300 South Park St., Madison WI
Bid Due Date: May 23, 2022
Construction Start Date: June 15, 2022
Expected Completion Date: October 15, 2022
"All information regarding dates/times are informational and should be verified with official RFB documents."
 
Village on Park Parking Structure
Planning and Design: April 18, 2022 - November 18, 2022
1st Advertisement of Bid: November 24, 2022
Bid Due Date: January 19, 2023
Construction Start Date: February 02, 2023

Expected Completion Date: June 07, 2024

LEED Goals: ParkSmart Certification

Public Involvement

City Process Meetings

Sep. 07, 2021 File #66450
Accepting the parking study and final parking count determination for the Village on Park

Village on Park Master Site Plan:

VOP Master Site Plan