Last Updated: 03/04/2022

Latest Update

2/2/2022 Update:

The Public Hearing dates at the Board of Public Works and Common Council have changed. Please see below the City Meetings section for the new dates. 

If you have questions or concerns regarding this project, please contact the Project Manager, Fadi El Musa, at felmusagonzalez@cityofmadison.com

Project Overview

In 2022, the City of Madison is proposing the construction of new concrete sidewalk at different locations throughout the City to fill gaps and connect existing sections of sidewalk. In addition, intersection crossings will be evaluated and improved as needed.

View the City of Madison Sidewalk Data Map which shows current locations with existing sidewalks.

Project Limits

Locations with missing sections of sidewalk have been identified as follows:

  • Busse St, east side of 3700 block
  • Johns St, both sides of 3600 block and a small section fronting 3526 Johns St.
  • Judd St., west side of 100 block
  • Walter St., east side Johns to Sargent.
  • Royster Ave., west side from Olbrich to Sargent.

Project Schedule

April 2022: advertised for bids.
June 2022: anticipated start of construction.

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

Public Information Meetings

Eastmoreland Community Association Public Information Meeting Presentation

City Meetings, Process

Transportation Commission: Presented on 10/27/2021
Board of Public Works: 3/16/2022
Common Council: 3/29/2022

Mailing

Project & Public Hearing Notice: 3/4/2022