Fire Station 10 Roof Replacement
Last Updated: 10/13/2021
Update October 13, 2021
Project Status: CONSTRUCTION!
Updated: Project History
October 12, 2021 File #67297Awarding Public Works Contract No. 8243, Fire Station 10 Roof Replacement
Roof Replacement
This project will replace the existing roof at Fire Station 10, add a skylight to provide day-lighting to interior living spaces, and provide safe roof access for maintenance personnel.
City User Agency: City of Madison Fire
Project Status: CONSTRUCTION!
1st Advertisement of Bid: 06/03/2021 available on Bid Express
Pre-Bid Building/Site Meeting:
Tuesday, August 10, 2021 @ 9:30 am at the project site, 1517 Troy Dr., Madison
Construction Start Date: 11/01/2021
Expected Completion Date: 07/15/2022
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."
Sustainability Goals:
This project will prepare the building for future installation of solar photovoltaic (PV) panels. It will also provide daylighting to interior spaces, reducing the need for artificial lighting.
Project History
October 12, 2021 File #67297
Awarding Public Works Contract No. 8243, Fire Station 10 Roof Replacement
April 26, 2021 File #64828
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for project known as Fire Station 10 Roof Replacement. (18th AD)