Campbell Street - Vilas Avenue
Latest Update
6/26/2020:
Construction is scheduled to start July 27, 2020. Construction is scheduled to be complete by Oct. 16, 2020.
This project was awarded to Parisi Construction Co., Inc.
Project Overview
This project includes the asphalt pavement reconstruction of Vilas Avenue between Garfield Street and the east side of Bear Mound Park and Campbell Street from Vilas Avenue to Drake Street. Spot repairs of curb and gutter, sidewalk, and driveway aprons will be included with this project, as well as utility replacements of storm sewer and sanitary sewer.
Project Limits
Vilas Avenue - Garfield Street to east end of Bear Mound Park (both legs)
Campbell Street - Vilas Avenue to Drake Street
Project Schedule
Construction begins: July 27, 2020
Scheduled Completion: Oct. 16, 2020
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
The City of Madison held a public information meeting Dec. 13, 2018.
Dec. 13, 2018 PIM Presentation